Contractors delay Spot renovations

Tony Reyes of Lockwood Construction was in the Student Center on Tuesday, Feb. 16, putting up drywall and frames for the new Spot. The construction site has been free from work for weeks, but since renovation has resumed an expected finishing date is the second week in March. The Aramark-funded renovation leaves students with one less place to eat, but when it is finished the Spot hopes to accommodate more students than before. / photo by Laura Ambriz
Tony Reyes of Lockwood Construction was in the Student Center on Tuesday, Feb. 16, putting up drywall and frames for the new Spot. The construction site has been free from work for weeks, but since renovation has resumed an expected finishing date is the second week in March. The Aramark-funded renovation leaves students with one less place to eat, but when it is finished the Spot hopes to accommodate more students than before. / photo by Laura Ambriz

by Michael Anklin
Staff Writer

Renovation completion of the Spot snack bar at the University of La Verne’s Student Center has been postponed until March, delaying plans of the scheduled re-open this month.

The snack bar was originally scheduled to undergo renovations last summer. But due to difficulties with Litzinger Associates Architecture, the contractors hired for the project, remodeling was deferred to January Interterm.

“We decided we wanted to have the least possible disruption for students and faculty,” said Dr. Loretta Rahmani, dean of student affairs, as to why construction was not started during the fall semester.

The delay is mainly due to problems with building permits.

“One of the big stumbling blocks was the L.A. County Health Department and the L.A County Public Works Department,” said Brian Worley, director of plan operations.

Original plans required that the University make many unexpected changes and adjustments to the Student Center, such as renovating some of its bathrooms.

“A lot of times, bureaucracy creates delays,” said Worley. “It [the Student Center] is a challenging structure to build within.”

The plans are still being reviewed by the city.

“My hands are tied until I have a permit in my hands to go any further. We’ve done what we could,” Worley said.

Dr. Rahmani said that although it may sometimes appear to students that there is no work being done at the actual construction site, things are getting done behind the scenes.

“A lot of things are going well with the project,” she said. “Equipment and furniture have been ordered.”

Worley pointed out that, for example, it takes six weeks for any cabinets that have been ordered to actually arrive.

As to when the Spot will be back in business, Worley said, “I’m keeping my fingers crossed. I’m looking at the second week in March, maybe the third week.”

Remodeling plans had been in the works for a long time.

“We were supposed to receive the plans for the architecture last May,” said Dr. Rahmani. Because of delays caused by Litzinger’s responsible project architect, the plans were finalized in early fall.

“The project architect was not very responsive,” said Worley, “and, in essence, he’s no longer with that company [mainly] because of that project.”

The new person in charge first had to become familiar with the project, adjourning its completion even further.

Concerning the dining services for the time being, Aramark Food Service Director Armen Ananian said the extended January operation hours for Davenport will remain until the new snack bar is finished. They are: 7-10 a.m. for breakfast, 10-10:30 a.m. for continental breakfast, 11:30 a.m. to 1:30 p.m. for lunch and 4:45-6:30 p.m. for dinner.

Similar to January, students may use their cash cards at Davenport for anything that exceeds their normal meal plan.

They are allowed to use them “for their friends or family,” Ananian said.

Michael Anklin, Editorial Director
Michael Anklin
Other Stories
Laura Ambriz, Photography Editor
Laura Ambriz

Latest Stories

Related articles

Construction raises the temperature in Tents

Construction affecting the insulation at the University of La Verne’s Sports Science and Athletic Pavilion, also known as The SuperTents, has caused some frustration among athletes, coaches and others who work or workout in the building. 

Facilities to spend summer safeguarding science labs following gas leak

Early in the morning on April 30, students in Founders and Mainiero halls were evacuated due to a gas leak, after the fire alarm was pulled. The fire department arrived quickly to resolve the issue. 

Athletic gym renovation to be completed this summer

Materials have been left in preparation for renovations in the new athletic weight room in the Athletic Pavilion. In the meantime, student athletes must train outside near track and field where a temporary outdoor gym has been created.

Most students say The Spot feeds them well

In a recent informal survey on campus, 12 out of 20 students said they enjoy most of the fare at The Spot dining hall, with the fresh fruit selection and the buffet style among the things they like best.