New structure to improve parking

Celene Vargas
Arts Editor

The new parking structure, to be built on campus starting in October, has some surprises that will benefit students and the University.

The four-story parking structure will have approximately 940 spaces in the structure and about 150 spaces in the surrounding lot. Most importantly, it will be free for students, according to Clive Houston-Brown, vice president for facilities and technology.

“That’s a decision we made in order to ensure that students park in our parking lots and in the structure,” Houston-Brown said. “If we charge them, many of them could continue to try to park in the neighborhood to avoid the parking fee.”

Once the parking structure is complete, there will be enough parking to accommodate a new residence hall.

“It’s important to note that the parking structure is beyond the capacity of what we have at the University right now,” said Chip West, assistant vice president of capital planning, facilities and space management. “It’s really going to take us way far in advance.”

The amount of parking spaces that will be available could also allow for the structure to have a section for faculty and staff.

In the meantime, commuters will have three shuttle lots to park at during construction: shuttle lot S, Campus West and one at Fairplex that the university is leasing.

“I’ve been late to class (waiting for the shuttle), but it’s been all right,” said senior computer science major Brandon Shulkin. “It kind of sucks…if you leave something in your car, and you’re parked all the way in the baseball field.”

ULV will be offering commuter lockers during the months of construction to fix this problem, since students will not have immediate access to their cars.

The lockers will be located in the Sports Science and Athletics Pavilion, for now, and should be ready by October.

“I think right now it’s rough, but I think the plans they have for the future, it’s going to work out,” said senior psychology major Zack Ward.

The parking structure will also have an 1,800 square-foot campus safety and transportation office space on the first floor, two elevators and a number of bicycle spaces and lockers.

There will be security cameras, LED lights and solar panels on top to cover the electrical usage for it.

“Unfortunately it’s not going to help me, because this is my last semester, but in the long run, I guess it’s going to help the community and the future students,” said senior psychology major Michelle Martinez.

The project remains on budget and on schedule.

“We did a lot of work over the summer in moving some of the lines that were under the ground, the sewer line and some of the utility lines to get it prepped for our construction start on Oct. 5, and we’re ready to go and have it ready by Aug. 15, 2016,” West said.

Celene Vargas can be reached at celene.vargas@laverne.edu.

Other Stories

Latest Stories

Related articles

Construction raises the temperature in Tents

Construction affecting the insulation at the University of La Verne’s Sports Science and Athletic Pavilion, also known as The SuperTents, has caused some frustration among athletes, coaches and others who work or workout in the building. 

Cres Gonzalez keeps ULV athletics running behind the scenes

A Leopard home game couldn't happen without the hard work of Cres Gonzalez.

Facilities to spend summer safeguarding science labs following gas leak

Early in the morning on April 30, students in Founders and Mainiero halls were evacuated due to a gas leak, after the fire alarm was pulled. The fire department arrived quickly to resolve the issue. 

Athletic gym renovation to be completed this summer

Materials have been left in preparation for renovations in the new athletic weight room in the Athletic Pavilion. In the meantime, student athletes must train outside near track and field where a temporary outdoor gym has been created.